Professional Scrum Master (PSM) I Practice Test 2025 - Free Scrum Master Practice Questions and Study Guide

Question: 1 / 400

What is the purpose of a Sprint Review?

To assess team performance

To gather feedback on the increment

The purpose of a Sprint Review is primarily to gather feedback on the increment produced during the sprint. This event involves the Scrum Team and stakeholders coming together to discuss what was achieved in the sprint, demonstrate the work that was completed, and solicit input on the deliverables. The feedback received is invaluable as it helps the team understand if they are aligned with stakeholder expectations and if any adjustments are needed moving forward.

During the Sprint Review, the team reviews the increment of work against the Sprint Goal, which offers an opportunity for stakeholders to see the current state of the product and contribute their perspectives. This iterative feedback loop is critical for ensuring that the product evolves in a way that meets the needs of its users.

Other potential purposes listed, such as assessing team performance, finalizing product requirements, or planning the next sprint, are typically addressed in different contexts within the Scrum framework. While these elements are essential to the overall process, they do not represent the primary objective of the Sprint Review itself. The focus remains on maximizing stakeholder engagement and ensuring the product increment provides value based on the feedback received.

Get further explanation with Examzify DeepDiveBeta

To finalize product requirements

To plan the next sprint

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy